#PB8-002D-3011
Price Code P6
EASY DECKS
•;Three;great;sizes;-
8';x;12'
12';x;12'
16';x;12'
•;Low;cost;construction
•;Can;be;built;with;standard;lumber
THE FOLLOWING LIST OF MATERIALS IS VALID ONLY WHEN USED IN ACCORDANCE WITH THE PROJECT BLUEPRINTS
deScriPtion;Qt Y
buildinG;MaterialS;-;8';X;12';deck
4x4x8' .................................................. 3 pcs.
2x6x12' ................................................ 5 pcs.
2x6x8'................................................ 28 pcs.
2x4x12' ................................................ 4 pcs.
2x4x8' .................................................. 4 pcs.
5" tie-down anchors.......................... 15 ea.
2x6 joist hangers................................. 6 ea.
5" corner framing anchors .................. 4 ea.
12d galvanized nails............................ 4 lbs.
16d galvanized nails............................ 2 lbs.
buildinG;MaterialS;-;12';X;12';deck
4x4x12' ................................................ 3 pcs.
2x6x12' .............................................. 35 pcs.
2x4x12' ................................................ 8 pcs.
5" tie-down anchors.......................... 21 ea.
deScriPtion;Qt Y
buildinG;MaterialS;-;12';X;12';deck
(continued)
2x6 joist hangers............................... 10 ea.
5" corner framing anchors .................. 4 ea.
12d galvanized nails............................ 6 lbs.
16d galvanized nails............................ 3 lbs.
buildinG;MaterialS;-;16';X;12';deck
4x4x12' ................................................ 4 pcs.
2x6x16' ................................................ 7 pcs.
2x6x12' .............................................. 35 pcs.
2x4x16' ................................................ 4 pcs.
2x4x12' ................................................ 4 pcs.
5" tie-down anchors.......................... 28 ea.
2x6 joist hangers............................... 10 ea.
5" corner framing anchors .................. 4 ea.
12d galvanized nails.......................... 10 lbs.
16d galvanized nails............................ 3 lbs.
NOTE: ALL LUMBER IS TO BE PRESSURE TREATED, ALL METAL FASTENERS ARE TO BE GALVANIZED
PROJECT
PLANS